The wastewater lagoons in the Town of Kindersley were badly in need of an upgrade.
The lagoons were outdated and in a poor state of maintenance, and the rural Saskatchewan community of 5,000 was growing.
By May 2020, Con-Tech General Contractors of Saskatoon had been hired to add a few lagoon cells to the existing systems. The company also built a lift station and laid new underground piping along with other upgrades to accommodate lagoon restructuring. The project also included cleaning of the lagoons.
Lagoons are typically cleaned by mechanical desludging and dredging, a costly and often difficult process. Seeking an alternative, Larry