SITHE Chopper Pump Ends Pump Clogging Issues at Shoe Factory Pump Station

This content is sponsored by Crane Pumps & Systems. Sponsored content is authorized by the client and does not necessarily reflect the views of COLE Publishing. View our privacy policy.
SITHE Chopper Pump Ends Pump Clogging Issues at Shoe Factory Pump Station

Interested in Pumps?

Get Pumps articles, news and videos right in your inbox! Sign up now.

Pumps + Get Alerts

The municipality of Darien is located in McIntosh County, Georgia, with a population of approximately 2,000 people and is located 50 miles south of Savannah. Darien has close to 20 wastewater pump stations and has a wastewater treatment plant with a 0.6 mgd capacity. 

The municipality was experiencing consistent pump clogging issues at the Shoe Factory pump station. The Shoe Factory pump station was the most problematic station for the city as its traditional solids handling non-clog pumps were clogging every couple of weeks. 

Lift station details

The Shoe Factory pump station is a duplex station with two 10 hp submersible solids handling non-clog pumps. The station receives inflow from a nearby law enforcement facility and various motels, and discharges directly to the wastewater treatment plant. Both pumps in the station were frequently clogging due to non-flushable solids including bedsheets, clothes, towels, deodorant bottles and shampoo bottles.

Clogs up to 3 feet in size were often found clogging the pumps. Solids loading was so severe that "the well looked like a garbage dump and a person can literally walk over the wastewater," according to Wayne Johnson, Darien's Public Works supervisor. There were instances when both pumps in the station would clog and the city had to bypass the station completely. This persistent clogging problem required the city maintenance team to monitor the station continuously to keep the pumps running.

Installation

Darien worked with Pump & Process Equipment, Barnes' municipal distributor in Georgia, to install a 4-inch 10 hp SITHE Chopper pump in the station in June 2018. The pump has not clogged since installation. The municipality is so impressed with the SITHE Chopper solution that they are planning to replace other problematic pump stations with SITHE Chopper pumps.

Key takeaways

Pain points:

  • The pumps in Darien's Shoe Factory pump station were clogging every two weeks
  • Non-flushable solids including bed sheets and deodorant bottles were clogging the pumps
  • Sometimes, both pumps would clog at the same time, requiring expensive bypasses

Solution:

  • Darien installed a 4-inch 10 hp Barnes SITHE Chopper pump in the station in June 2018
  • The SITHE pump has not clogged once since installation
  • Darien plans to replace other problematic pumps with SITHE Choppers in the future


Visit the Crane Pumps & Systems Storefront


Discussion

Comments on this site are submitted by users and are not endorsed by nor do they reflect the views or opinions of COLE Publishing, Inc. Comments are moderated before being posted.